Abstract
The heavy water plant was established under the name of Combinatul Chimic Drobeta, by Decree 400/16.11.1979, under the Inorganic Products Industrial Center (CIPA) Râmnicu Vâlcea. The thermo-electric plant for supplying the heavy water factory with steam was decided to be located in Halânga village, three kilometers from the factory. The process water required for the factory was brought from the Danube, and the hydrogen sulphide used in the process was produced in the plant, through a specific technology, and then compressed, liquefied and stored in special tanks. The works on the heavy water factory at Drobeta Turnu Severin started in 1979, based on a derogatory HCM. The equipment for the heavy water plant was purchased through the Industrial Center for Chemical and Refinery Equipment (CIUTCR). All equipment and facilities that transported hydrogen sulphide had to meet strict quality assurance conditions.